Project Name: Seward Highway,
Six Mile Trail, M.P. 56 to 64
Description: Bulb-tee bridge
addition
Award Date: 1999
Original Subcontract Amount: $760,984.00
Project Name: ARRC Seward
Baggage Handling Modifications
Description:
Award Date: 1999
Original Contract Amount:
$$112,261.00
Project Name: Seward Railroad Dock Dredging,
Seward Alaska
Description: Maintenance dredging for the
Alaska Railroad Corporation
Award Date: 1995
Original Contract Amount: $647,175.00
Project Name: Princess Tours Dock Fender System,
Seward, Alaska
Description: Replacement of Existing Fender
System
Award Date: 1994
Original Contract Amount: $494,000.00
Project Name: Lowell Creek Tunnel Rehabilitation,
Seward, Alaska
Description: Dewater, clean and rehabilitate
the tunnel invert with 10,000 psi silica fume concrete
Award Date: 1991
Original Contract Amount: $705,000.00